Website RFP template for a B2B SaaS redesign: what to include, what to leave out.

A good website request for proposal (RFP) for a B2B SaaS redesign tells agencies what the website redesign project must achieve, what exists today, what can't break, what you can spend, and how you'll choose. This guide gives marketing leads and founders the sections to include, the requirements most RFPs miss, a fair scoring method, and a one-page brief.


What should a website redesign RFP template include?

Everything an agency needs to scope and price the same project, and nothing that prescribes the answer. Public procurement teams describe the core of an RFP as a statement of work with measurable objectives, plus background, questions for proposers, submission instructions, a schedule, and published evaluation criteria. A B2B SaaS website RFP template needs the same backbone, with a few sections specific to web design and web development.

The sections of a website RFP and why agencies need each one
SectionWhat to includeWhy agencies need it
Project overview and goalsWhat the company sells, the target audience, and two or three measurable project goals tied to business goals (for example, lead generation from organic search, measured as demo requests)To propose a site that serves a business result, not just a new look
Current websitePage count, content management system, share of leads from organic search, top pages by traffic and conversionsTo size migration and SEO risk on the existing site
ScopeTemplates and page types, who writes and migrates content, languagesTemplates and content drive most of the effort
IntegrationsCRM, marketing automation, product sign-up, docs, chat, analyticsEach integration adds build and test time
SEO and migrationURL map, redirect rules, what must keep rankingTo protect traffic through launch
Accessibility and performanceA named standard and named targetsSo every agency prices the same level
Analytics and consentKey events, consent banner, regionsTracking is rebuilt on every redesign
Security and procurementQuestionnaire, MSA, DPA, who signsPaperwork can take longer than design
Budget and timelineA budget range and the project timeline, with the dates that matterTo make proposals comparable
EvaluationCriteria, weights, and the decision processSo agencies know what to emphasize
Submission requirementsFormat, submission deadline, questions process, contactTo keep the process fair

Attach what you can: an export of current URLs, a summary of the last 12 months of Search Console and Google Analytics data, and the brand guidelines. A URL list lets agencies size the migration; "about 300 pages" leaves them guessing.

Which technical requirements do most website RFPs leave out?

The ones that protect pipeline after the new site launches. Generic RFP templates cover goals, design, and budget well, but they rarely ask for these:

  1. A URL map and redirect rules. Google's site-move guidance says to map every old URL to its new URL, use permanent server-side redirects (301 or 308) straight to the final address, and keep them for as long as possible, generally at least one year. Ask each agency how it builds, tests, and hands over the redirect map, and who owns it.
  2. Crawl access for search and AI features. Google says there are no extra requirements to appear in AI Overviews or AI Mode, but crawling must be allowed in robots.txt and by any CDN or hosting layer. Ask for content to be in the HTML and for a clear robots.txt policy.
  3. An accessibility standard. Name WCAG 2.2 level AA. WCAG 2.2 became a W3C Recommendation on October 5, 2023, and six of its nine new success criteria are at level A or AA. "Accessible" without a standard means each agency prices something different.
  4. Performance targets. Use Google's Core Web Vitals thresholds: Largest Contentful Paint within 2.5 seconds, Interaction to Next Paint under 200 milliseconds, and Cumulative Layout Shift under 0.1.
  5. Analytics and consent. List the key events (demo request, sign-up, contact), the CRM fields forms must fill, and where your consent banner applies. Google's consent mode documentation puts the responsibility for collecting consent on the site owner, so decide who sets it up and tests it.
  6. CMS roles and workflow. Who edits, who approves, and whether you need scheduled publishing, localization, or audit logs. On Webflow, features such as custom roles, publishing workflows, audit logs, and contractual uptime SLAs are part of the Enterprise plan.
  7. Data processing terms. If the agency will handle personal data, such as form submissions or analytics access, the European Data Protection Board says the controller and processor relationship must be governed by a contract, and sub-processors need the controller's written authorization. Ask whether the agency signs a DPA and which legal entity signs.

Should you include a budget in a website request for proposal?

Yes, as a range. Without a budget, one agency scopes a template refresh and another scopes a rebuild with new content, and the proposals can't be compared. A range lets each agency show what it would do at that level and where it would draw the line.

If you can't share a number, share what drives the cost instead, so agencies can scope consistently:

  • the number of unique templates, not total pages;
  • who writes new copy and who migrates existing content;
  • the number and depth of integrations;
  • languages and regions;
  • how many review rounds and approvers the design needs;
  • security reviews and procurement steps.

What should you leave out of a website RFP?

Anything that answers the questions you're paying an agency to answer, or that adds work without helping you choose.

  • Finished design decisions. Describe the problem ("buyers can't find pricing for teams over 50") rather than the layout ("add a mega menu"). You want to compare thinking, not obedience.
  • Unranked wishlists. Forty features with equal weight make every proposal hedge. Mark each requirement as must-have, should-have, or nice-to-have. The ranked list also helps with scope creep later, because the contract can point to what was agreed.
  • Unpaid spec design. Asking for mockups before selection rewards speed over understanding, and the work is done without access to your data or your marketing and sales teams.
  • The full security questionnaire, too early. Send it to the shortlist. A long questionnaire at the RFP stage costs every agency days and tells you little about fit.
  • Vague success measures. "A modern site that converts" can't be scored. "More demo requests from organic search on the new website than on the current site, measured over 90 days" can.

How do you score agency proposals fairly?

Agree the criteria and weights first, publish them in the website RFP, and score independently. New York State's procurement guidance says evaluation tools should be built before the RFP is released, and the University of Texas System publishes its evaluation criteria and weights in the RFP itself. Private companies don't have to follow public rules, but the same habits keep the choice of an agency partner from coming down to the best presentation.

Example scoring weights for a B2B SaaS website RFP
CriterionExample weightWhat a strong answer shows
Understanding of goals and buyers20%Restates your goals in its own words and asks sharp questions
SEO, migration, and analytics approach20%A specific redirect, tracking, and launch plan
Relevant work20%Similar companies, similar scope, live sites you can check, and client references you can call
Team and process15%The key team members who do the work, project management, and how reviews and decisions run
Timeline realism10%A proposed timeline with phases and dependencies, including your inputs
Cost and value15%A clear scope behind the number

These weights are an example, not a standard. Adjust them to what matters most to you, then keep them fixed while you score. Have each evaluator score alone before the group compares notes, so the loudest view doesn't set the result.

What timeline should the RFP process follow?

Give agencies enough time to ask questions and propose properly, and give your own team time to read. An example schedule:

  1. Week 0: send the RFP to a short list of potential vendors.
  2. Week 1: deadline for written questions.
  3. Week 2: publish all answers to all prospective vendors at the same time.
  4. Week 3 or 4: submission deadline for proposals.
  5. Week 5: shortlist calls or presentations with the people who would do the work.
  6. Week 6: decision, then contracts, DPA, and security review.

Start procurement steps early. If your company needs a security review, an MSA, and a DPA, begin them while proposals are being written, so signing doesn't delay the kickoff.

What does a one-page website design RFP brief look like?

One page is usually enough for an agency to judge fit and the rough shape of the website project. Send this free website RFP template first, and the detailed RFP with full requirements to the shortlist.

One-page website RFP brief to copy
FieldFill in
Company and productOne sentence on what you sell and to whom
Why nowThe trigger: rebrand, new market, platform change, poor conversion
GoalsTwo or three measurable goals and how you'll measure them
Current siteURL, CMS, page count, share of leads from organic search
Must not breakTop pages, integrations, forms, and URLs that carry traffic
ScopeTemplates, content (who writes), languages, integrations
StandardsWCAG 2.2 AA, Core Web Vitals targets, consent regions
PlatformPreferred content management system, or "open to recommendation" with your reasons
Budget rangeA range, or the cost drivers above
Key datesProposal deadline, decision date, launch window and why
Decision processWho decides, the criteria and weights
ContactOne person for questions, often the project manager, and the questions deadline

We run website redesigns and migrations for B2B and SaaS companies, so we have an interest in this topic. For how we scope and run a redesign, see our website redesign page, and for enterprise procurement documents, our Webflow Enterprise guide.

Questions about website RFPs

What should a website RFP include?

Company background and goals, facts about the current site, the scope, technical and SEO requirements, accessibility and performance targets, analytics and consent needs, security and procurement requirements, a budget range, the timeline, evaluation criteria with weights, and submission instructions.

How long should a website RFP be?

Long enough to price the work and no longer. For most B2B SaaS redesigns, a one-page brief plus a few pages of requirements and attachments, such as a URL list and analytics summary, is enough.

Should you share your budget in a website RFP?

Yes, as a range. Without one, agencies scope to very different levels and the proposals can't be compared. A range lets each agency show what it would do at that level.

How many agencies should receive a website RFP?

Enough for a real comparison and few enough to read every proposal carefully. A short list chosen from past work and a brief call usually beats a wide send.

How should you score website redesign proposals?

Agree the criteria and their weights before the RFP goes out, publish them in the RFP, and have each evaluator score the proposals independently before the group compares notes.

Sources

  1. Google Search Central: Site moves with URL changes Accessed October 18, 2026
  2. Google Search Central: AI features and your website Accessed October 18, 2026
  3. Google Search Central: Understanding Core Web Vitals and Google search results Accessed October 18, 2026
  4. W3C WAI: What's New in WCAG 2.2 Accessed October 18, 2026
  5. Google Tag Platform: Consent mode overview Accessed October 18, 2026
  6. European Data Protection Board: Data controller or data processor Accessed October 18, 2026
  7. New York State Office of General Services: A Guide to RFPs for Procurement Professionals Accessed October 18, 2026
  8. The University of Texas System: Request for Proposal (RFP) Accessed October 18, 2026
  9. Webflow Help Center: Differences between Enterprise and non-Enterprise plans Accessed October 18, 2026
  10. BenorMedia: Website Redesign Services for B2B & SaaS Accessed October 18, 2026
  11. BenorMedia: Webflow Enterprise: What to Check Accessed October 18, 2026
GET IN TOUCH

Ready to build your website? Let's chat.

See Pricing

Trusted by +100 companies

Resources

Related resources.

  • ServicesWebsite redesign for B2B and SaaS teams, built on what already works.Website redesign services for B2B and SaaS teams. We keep the pages that rank and convert, rebuild the rest, and launch on Webflow or custom code.Learn more
  • WebflowPublished on 10/07/26Sergio GancedoWebflow Enterprise: security, governance, and what to check before you commit.What makes a website project enterprise, what Webflow Enterprise includes as of October 2026, and how to vet an agency. Sourced from Webflow, Google, and W3C.Learn more
  • ServicesWordPress to Webflow migration, planned around your search traffic.WordPress to Webflow migration for B2B teams. Every URL mapped, every redirect tested, and a plan built around the pages that earn your traffic.Learn more

Let's work together.

Please fill out the form below and one of our team members will be in touch with you within 24 hours. You can also reach out at info@benor.media

Engagement Budget*

“BenorMedia is a valued partner to us at Surfe. Communication is always easy, things get implemented quickly, and their ongoing support has become an important part of our day-to-day operations.”